Question

1 Approved Answer

Taveras Corporation is currently operating at 5 0 % of its available manufacturing capacity. It uses a job - order costing system with a plantwide

image text in transcribed
Taveras Corporation is currently operating at 50% of its available manufacturing capacity. It uses a job-order costing system with a plantwide predetermined overhead rate based on machine-hours. At the beginning of the year, the company made the following estimates:
Machine-hours required to support estimated production Fixed manufacturing overhead cost
195,000
$3,510,000
$2.00
Variable manufacturing overhead cost per machine-hour
$2.00
Required:
Compute the plantwide predetermined overhead rate.
During the year, Job P90 was started, completed, and sold to the customer for $3,100. The following information was available with respect to this job:
Direct materials
$1,426
Direct labor cost
$1,023
Machine-hours used
78
Compute the total manufacturing cost assigned to Job P90.
Complete this question by entering your answers in the tabs below.
Required:
Compute the plantwide predetermined overhead rate.
During the year, Job P90 was started, completed, and sold to the customer for $3,100. The following information was available with respect to this job:
Drect materials
$1,426
Direct labor cost
Machine-hours used
$1,02378
Compute the total manufacturing cost assigned to Job P90.
Complete this question by entering your answers in the tabs below.
Required 1
Compute the plantwide predetermined overhead rate.
Predetermined overhead rate
per MH
Required:
Compute the plantwide predetermined overhead rate.
During the year, Job P90 was started, completed, and sold to the customer for $3,100. The following information was available with respect to this job:
Direct materials
Direct labor cost
Machine-hours used
$1,426
$1,023
78
Compute the total manufacturing cost assigned to Job P90.
Complete this question by entering your answers in the tabs below.
Required 1
Required 2
Compute the total manufacturing cost assigned to Job p90.
\table[[Direct materials,,],[Direct labor,,],[Overhead applied,L,],[Total manufacturing cost,$,0]]
Required:
Compute the plantwide predetermined overhead rate.
During the year, Job P90 was started, completed, and sold to the customer for $3,100. The following information was available with respect to this job:
Direct materials
Direct labor cost
Machine-hours used
$1,426
$1,023
78
Compute the total manufacturing cost assigned to Job P90.
Complete this question by entering your answers in the tabs below.
Required 1
Required 2
Compute the total manufacturing cost assigned to Job p90.
\table[[Direct materials,,],[Direct labor,,],[Overhead applied,L,],[Total manufacturing cost,$,0]]
image text in transcribed

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image_2

Step: 3

blur-text-image_3

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Advanced Financial Accounting

Authors: Theodore E. Christensen, David M. Cottrell, Cassy JH Budd

11th edition

78025877, 978-0078025877

More Books

Students also viewed these Accounting questions

Question

What are the four phases of the active listening process?

Answered: 1 week ago