TB MC Qu. 21-130 (Algo) Sanchez Company's output for the... Sanchez Company's output for the current period was assigned a $380,000 standard direct materials cost.
TB MC Qu. 21-130 (Algo) Sanchez Company's output for the...
Sanchez Company's output for the current period was assigned a $380,000 standard direct materials cost. The direct materials variances included a $9,500 favorable price variance and a $5,700 unfavorable quantity variance. What is the actual total direct materials cost for the current period?
Multiple Choice
-
$395,200.
-
$376,200.
-
$383,800.
-
$364,800.
-
$389,500.