(TCO A) Tim Construction Co. began operations in 2016. Construction activity for 2016 is shown below. Tim uses the percentage of completion method. Contract Contract
(TCO A) Tim Construction Co. began operations in 2016. Construction activity for 2016 is shown below. Tim uses the percentage of completion method.
Contract | Contract Price | Billings Through 12/31/16 | Collections Through 12/31/16 | Costs to 12/31/16 | Estimated Costs to Complete |
---|---|---|---|---|---|
1 | $5,200,000 | $3,500,000 | $2,600,000 | $3,000,000 | $1,000,000 |
2 | $3,600,000 | $1,500,000 | $1,000,000 | $820,000 | $1,880,000 |
3 | $3,300,000 | $1,900,000 | $1,800,000 | $2,250,000 | $1,200,000 |
What amount of Gross Profit should Tim show on the Income Statement of 2016 related to Contract 3?
$0 |
$150,000 loss |
$150,000 profit |
None of the above |
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started