TE Accounting is evaluating their budget for the next year and determining which projects should be picked. Let yj= 1 if project j is selected,
TE Accounting is evaluating their budget for the next year and determining which projects should be picked.
Let yj= 1 if project j is selected, 0 if not, for j = 1,...,5.
Write the appropriate constraint(s) for each condition. Conditions are independent.
a.Choose no fewer than three projects.
b.If project 3 is chosen, project 2 must NOT be chosen.
c.If project 1 is chosen, project 4 must be chosen.
d.Projects cost 450, 320, 680, 850, and 670 respectively.
The budget is 2750.
e.No more than two of projects 1, 2, and 3 can be chosen.
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started