Answered step by step
Verified Expert Solution
Link Copied!

Question

1 Approved Answer

Team Assignment 1: American Constructors, Inc. Prepare a Word document that states the project objective. Write from the perspective of the project manager in the

Team Assignment 1: American Constructors, Inc.

  1. Prepare a Word document that states the project objective. Write from the perspective of the project manager in the case. We are joining this project part-way through, so the objective can reflect that but don't need to focus on that - in the end the goal is to finish the entire project.

2. Setup the blank MS Project file to start, as explained in class:

  • Input the project start date (Project-Project Information), Auto-Schedule, project name in file.

(As you work in MS Project this term, save the file often, and save copies - use different file names)

  1. Using the Gantt chart view in MS Project, make the task list (this is your WBS):
  2. Create a "Title Task" at the top with the name of the project. (Can use Gantt Chart Format - Project Summary Task). All other tasks are sub-tasks under this one.
  3. Start the project plan with a single, one day task on Sept 24, call it "Tom's planning meetings", or "Meetings with Team, Architect & Client", or something similar. For our purposes, we will have all other tasks (including ongoing tasks that would have started before Sept 24) occur after this, starting no earlier than Sept 25.
  4. All the work on the Lobby should be entered as just one task (called "Lobby Construction" or something similar) - this task should be 62 days long.(the reason for this is to make the assignments easier for you)
  5. Entire project must be set up in terms of tasks, sub-tasks, sub-sub tasks, etc.
  6. Due to the high level of detail given in this case, it is possible to make a reasonable project plan with only the information given. But, as always, there are details skipped in the discussion - use your intuition and creativity to add a few tasks that "round out" and complete the plan more fully - or you may want to break up some of the tasks into more than one task. Add 2-5 tasks and/or sub-tasks (there aren't "right" or "wrong" tasks, just be reasonable).
  7. Be sure to include a project review task (after project is done) that takes a day or so.
  8. Link the tasks by inputting predecessors.
  • Your project should have multiple paths wherever possible.(ONLY link lowest level tasks, do not link supervisory tasks)
  • It may help to show the Successors column immediately to the right of the Predecessors column (right click on the title of the Resource Names column, choose Insert Column, choose Successors
  • Copy the objectives (& assumptions) into the project file by:
  • Select the "Title Task" and open "Task Notes"
  • Paste the text in (do not use the "Insert Object" button)

  1. Input the maximum task durations as given in the case (do not use any minimum times, crashed times or "expedited" times given). Make up reasonable durations for your 2-5 added tasks.
  • ONLY input durations for the lowest level tasks - not for supervisory tasks.
  • Use the default "As Soon as Possible" task constraint for ALL tasks. If you feel you need any other type of constraint, first email me to ask if it is OK.

  1. Create a list of resources in the Resource Sheet view, or by typing them on the Gantt Chart:
  • See Appendix at end of this assignment.
  • Work Resources: Use the personal names given in the case, and use names of departments, companies or groups where it is reasonable.
  • MUST have at least one Cost resource and at least two Material resources. It is best to add these using the Resource Sheet.
  • Assign resources to tasks
    • Be sure to assign people/work resources to ALL tasks except supervisory
    • Material Resources are assigned where they are used.
    • Cost Resources are assigned when appropriate.
  • Do NOT worry about people who are over-assigned
  • Do NOT assign % of units, costs, hourly wages, etc.

  1. Enter at least 2 milestones (by adding tasks), one of which marks them completely ready for the architect's punchlist(milestones do not usually need a resource, but is OK to assign one if appropriate)

  1. Input a "project-end" deadline for the completion of the Fire Marshal's inspection. (Once the Fire Marshall has approved that the building is safe, the church can start using it even while the architect's punch-list is being worked on, so the crucial deadline is completion of the Fire inspection.) Also add at least one other deadline somewhere else in the project that is not met with the current project plan.

  1. Show the critical path in the Gantt chart (View-Gantt Chart-More Views-Detail Gantt).(Then, in order to show the spreadsheet portion "normally", change the view to View-Tables-Entry.)

Do NOT adjust (or crash) any activities. Do NOT save a baseline. Do NOT worry about over-allocated resources.

APPENDIX:

Types of Resources in MS Project:

  • Work: Human resources (usually hourly, sometimes cost per use)

  • Material:Supplies or other consumable items that are used to complete tasks in a project

  • Cost:Costs that don't depend on the amount of work on a task, or the duration of a task, or that don't need to occur on a specific date, such as:
    • a capital expenditure on equipment
    • variable costs such as airfare or lodging
    • fixed price contract with subcontractor

image text in transcribedimage text in transcribedimage text in transcribedimage text in transcribedimage text in transcribedimage text in transcribed
IVEy | Publishing 98190016 AMERICAN CONSTRUCTORS INC.: WORLD OUTREACH EXPANSION PROJECT Leanne Micie wrote this ca ely to provide material for class discussion. The authors do not intend to situation. The authors may have disguised certain Fi Richard Wvey School of Business a storage or fransm n without it's written permission. Reproduction of this material is not covered under a cation by any reproduction rights organization. To order copies or request permission to reproduce materials, contact ivey Publishing, Richard Ivey School of Business Foundation, The University of Western Ontario, London, Ontario, Canada, MGA 3:7, phone (519) 651-3208 fax (519) 661-3862; c-mail cases @ivey.two.ca. Copyright @ 2010, Richard Wey School Version: 2019-09-27 It was 8:00am on September 24, 2009. Tom Grott, senior project manager for American Constructors, Inc (ACT), sat down with his team to assess the progress on their current project at World Outreach Church (WOC) in Murfreesboro, Tennessee. That afternoon, Grott needed to meet with the architect and the client to report on the company's probability of completing the work by the project finish date, December 14, 2009, he also needed to discuss the close-out requirements with the architect. The impending deadline was Authorized for use only by Ishiga Patil in OPER3P92 at Brock University from 915/2023 to 12/24/2023. Use outside these parameters is a copyright violation creating significant tension on the site. Originally scheduled for March 2010, the date was pushed up to December as per the client's request in spring 2009. Initially they requested that the property be completed for use on the Thanksgiving holiday (November 26, 2009). Grott recognized the impossibility of their request and compromised by adding a few additional weeks to that date. He knew that the church was relying on him to have the project completed for the Christmas season. WOC was established in 1980 as an inter-denominational Christian congregation. As of late 2009, the church had more than 5,000 members and was broadcast every Sunday morning on three different television channels. In addition to its television broadcasts, WOC offered a 24/7-radio show and MP3 downloads of selected sermons. The church had become a major establishment in middle Tennessee, with claim to several high-profile congregants. Grott's leadership on this project would leave an impression on the local and church communities. In an effort to uphold the reputation of ACT and protect future opportunities, Grott needed to ensure that the project was completed on time. AMERICAN CONSTRUCTORS, INC. ACI was founded in 1979, and by 2009 was enjoying the benefits of being one of the leading commercial construction companies in middle Tennessee. Since its inception, the company contracted more than 600 projects, totalling in excess of USSI billion'. The company became licensed in 15 states across the United States. Some of its famous contracts included major Nashville landmarks such as The Country Music Hall of Fame & Museum and The Schermerhorn Symphony Center (see Exhibit 1). The company also successfully contracted the construction of several music publishers' headquarters in the Nashville area, AN monetary values in US$ unless otherwise statPage 2 98100016 namely the American Society of Composers, Authors and Publishers (ASCAP), Sony-Tree and Electrical & Musical Industries, commonly known as EMI. In the first 30 years of operations, the company worked hard to carn multiple awards, which recognized its dedicated staff and the calibre of its work. Some of these awards included multiple awards of excellence in development as well as awards in safety, safety training and evaluation processes. Although a drastic slump in the construction market in 1988 threatened the future of the firm, the ACI team worked diligently to keep the company alive. In 2009, ACT was a strong and growing firm with several projects across the state of Tennessee. THE CHURCH CONSTRUCTION MARKET ACI focused its contracts in five construction markets; public and private schools, churches, health care facilities, entertainment and office buildings/complex properties. The company's first church construction project came in the carly 1990s. It was during this project that they met the firm's president as of 2009, Dan Brodbeck, as he was serving on the building committee for the church. Due greatly to the success of the project and the relationships forged during this time, Brodbeck was persuaded to join the ACI team. Throughout the 1990s, area churches continued to be a strong market for the company: it completed four more properties by 1996 and continued accepting major church expansion projects into the new millennium. Construction of religious centres had been a booming industry across the United States. In 2006, the church construction market was estimated at more than $7.6 billion alone. The American Institute of Architects (AIA) released a forecast in 2009, predicting that the religious construction sector would Authorized for use only by Ishiga Pal in OPER3P92 at Brock University from 9/5/2023 to 12/24/2023. Use outside these parameters is a copyright violation experience higher growth than all other non-residential sectors in 2010-, showing that despite a struggling market, church construction could provide jobs for construction firms such as ACT, making them a highly valuable client. The WOC expansion was initially budgeted as a $31 million project; however, changes in the architect's design and a few unforeseen events resulted in an increase to $34 million. WORLD OUTREACH CHURCH EXPANSION PROJECT With 20 years of experience in the construction industry and a bachelor's degree in construction management, Grott was one of the most skilled managers on the ACT staff. Although Grott anticipated that it would be challenging to please the client by meeting the December 14 deadline, he was confident in his team of administrative staff, his crew of 10 labourers (carpenters, finishers, cleaners and machine operators) and the 25 different subcontractors. Exhibit 2 shows some of the progress as of September 2009. It was crucial that the building be usable by the congregation for the Christmas season even if there was some minor work still ongoing. At the completion of the church expansion project, the architect would provide Grott a punch list of minor tasks that the architect and WOC believed needed to be completed before the property would officially be considered complete. As part of running through the punch list, ACI would also do a last run-through of the property to ensure quality. Grott's goal was to start this final task, the architect's punch list, by the project deadline on December 14. He estimated that the architect's punch list would require five to 10 days, depending on their demands, and he was hoping the tasks required could be done while the congregation started using the building A critical part of any contractor's job is coordinating the close-out of a project. In preparation for his meeting with the architect that afternoon, Grott had prepared a memorandum outlining their close-out http:/info.aja. org/aiarchitectthis eekon of 1601 16 consensusPage 3 9810D016 responsibilities (see Exhibit 3). The items listed needed to be completed and submitted immediately, and had to be received back before the fire marshal's inspection of the property, which in turn would happen before work on the architect's punch list (see further details below). Grott would submit his request to the architect that afternoon and expected the documents to be mailed to his office in no later than four weeks (20 days), but no earlier than two weeks. In terms of capital projects of this size, it is not uncommon for construction to remain active several months after close-out documents are prepared; however, as noted in the memo, the General Guarantee and Warranty and the Final Release of Lien (two other important documents) could not be signed until the architect's punch list was completed. The General Guarantee and Warranty was a document submitted to WOC by ACI affirming that the work they performed was in accordance with the details outlined in the original contract (see Exhibit 4). This type of document was important for a job this large, as it granted the client, WOC, a full year to inspect and evaluate the workmanship of the property. It also relinquished any responsibilities for ACI after one year. Although preparing this document would not take much time and would not affect the construction schedule, getting it signed after the architect's punch list was completed would be an important sicp that could take somewhere between half a day to one day, since the WOC would undoubtedly want to look over the whole project carefully before signing. The Final Release of Lien was also a very important legal document (see Exhibit 5). It would be signed by each subcontractor to record that they received their money and performed their duties, indicating that they no longer had any financial interest in the property (this would not affect the construction schedule). Remaining Construction Authorized for use only by Ishiga Pal in OPER3P92 at Brock University from 915/ 2023 to 12/24/2023. Use outside these parameters is a copyright violation In discussing the current progress with his team, Grott identified three main sections of the property that remained unfinished as of September 24, 2009. These sections included the bookstore/cafe/kitchen, the lobby and the sanctuary. Bookstore/Cafe/Kitchen In planning the final stage of the bookstore cafe kitchen section, Grott explained that work was already in progress on framing, hanging and finishing the drywall. He predicted that it would take the subcontractor, Cage Drywall, at least 21 more days to complete the work (at most 23 days). Once it was finished, installing the hard tile and finishing the stone columns would be started. These tasks would take 10 days and five days, respectively. At the same time that the hard tile and stone columns were started, Bridget Brodbeck, the project coordinator, explained that she had scheduled Integrity Architectural Millwork to begin millwork on the bookstore, cafe and kitchen, she estimated that they required 15 to 21 days to complete the work. Following the millwork, casework (installation of cabinetry) could begin. Brodbeck estimated further that they needed five days to complete this task. Installation of flooring would take 10 days and would begin after the casework was finished. Upon completion of the hard tile and stone columns, installation of the glass was scheduled to begin. Expected to take no more than three days, the glass installation included windows and glass slabs for the storefront. Grott and Brodbeck arranged for Charlie Irwin Painting to come in after the glasswork was completed. Painting this area of the church would take 10 days. Integrity Architectural Milwork is a company located . TN that specializes in woodwork, including reception desks, architectural paneling and custom moldings. They are a milwork firm that has been used by ACI in a number of other large projects.Page 4 9810D016 Once the painters and flooring installers vacated the area, Grott's crew of carpenters would begin installing the doors and associated hardware. Larry Hawker was the project superintendent who oversaw the work of the crew on the site, his 38 years of experience had taught him that this task time could vary greatly. Hawker explained to the team that if the received doors were of the correct requirements and no hardware was missing, the carpenters would require five days to install them in the bookstore cafe kitchen area; otherwise, reordering and matching hardware to each door could make the task take an additional two days. At maximum, Hawker expected that the doors and hardware could take eight days, factoring in all potential problems. While the carpenters were working on installing the doors, Brodbeck had scheduled mechanical, electrical and plumbing (M.E.P.) work to take place.* On the work breakdown schedule, Brodbeck pointed out that 10 days were allocated to the subcontractors for these jobs. As with the other sections of the project, the bookstore cafe kitchen would be completed with a thorough cleanup and run-through of the company's own punch list created by Grott and Hawker. Cleanup and completing the tasks on the ACI punch list for the entire project would each take approximately four days, and could be done simultaneously, but only after all three major sections of the project were completed. These tasks would be followed by a fire marshal inspection, which could take up to five days for a property of this size. Only after the inspection could the architect's punch list begin. As internal inspections were conducted at various stages throughout the project, the inspection of ACI properties by the fire marshal had historically always passed. Lobby The lobby of the expanded church was two floors high. ACT was currently working on the reception area Authorized for use only by Ishiga Pail in OPER3P92 at Brock University from 915/2023 to 12/24/2023. and the ceilings. Grott predicted that it would take 10 days to complete the reception area. Millwork was Use outside these parameters is a copyright violation the major task that remained unfinished: the millwork task included work on the reception walls, counter, columns and rails. While the full 10 days could be spent on the walls and rails, the work on the reception counter would only take three days and was slotted to be done in parallel with the other millwork. Work on the hard ceiling was almost complete and would also take the next 15 days. At the same time as these two tasks, Cage Drywall was scheduled to install the drywall in the lobby. (Cage Drywall had enough employees and subcontractors that they could work on multiple sections of the church simultaneously. This was also true for all the other subcontractors.) Within the following 15 days, the subcontractor was expected to hang and finish the drywall. As the team continued to review the schedule, Brodbeck discussed the plans for painting the lobby. Following the above three tasks, the painters were scheduled to paint both the first and second floor of the lobby and were contracted to take five days. Flooring, another major task required to complete the lobby, was scheduled to begin once the millwork at the counter was completed. A thin concrete layer had to be laid in areas where carpeting was going to be put in so that the carpet was the same height as the flooring. Hawker described the process to the team, indicating that the task times could vary from as little as five days to as much as eight days, considering that the crew's ability to lay the concrete depended on the weather conditions, since much of the preparation was done outside. The hard tile in the lobby would be laid following the completion of drywall installation: they expected this task to take five days. The work would be completed by a subcontractor. Once the crew had finished their work with the concrete insert at the carpeted areas, a treatment would be applied to the wood flooring materials to acclimatize the wood, and the flooring would be installed. This task would take 35 days, including 10 days allocated for the wood treatment. The 25-day installation could take up to three additional days if the material was not laid with precision. Hawker noted that this time The major subcontractors for these tasks included Roscoe Brown Heating & Cooling and SAW Electric.Page 5 98100016 could also be shortened if needed by employing the crew to work overtime and help the subcontractor. With incentive, the subcontractors could usually be persuaded to get the job done sooner. Hawker estimated that the installation could be crashed to 30 days. Carpeting of the first floor, the stairwell and the second floor of the lobby were scheduled to begin following installation of the wood flooring and the hard tile, and would take approximately nine days. Grott continued the meeting by discussing the finishing tasks involved in the lobby construction. Once the drywall and hard ceilings were completed, the crews would switch to work on and finish the public restrooms: this was expected to take nine days. At the same time, installation of glass and hanging the chandeliers would be done and was expected to take three days. The glass panels would span the height of the first floor and create a bright space by serving as the front wall of the building. The ceiling tiles also needed to be installed, and Grott and Brodbeck explained to the team that Acoustical Ceiling Tile was scheduled to work for five days following the completion of painting. After the ceiling tiles, washrooms, flooring and carpeting were done, the last two steps in finishing the lobby would begin. Done in parallel with each other, the doors and hardware needed to be installed and the M.E.P. work completed. Each of these two tasks were expected to take approximately 10 days for the lobby area, but they could be done in tandem with each other and with similar work in other sections of the building. After this, the cleaning and ACI punch list could be started, as explained above. Sanctuary The sanctuary was a large auditorium with ticred seating and a balcony with additional scating: it was designed to be the largest section of the expansion and therefore required a great deal of work and detail. Upon completion, the sanctuary, with its auditorium seating and large stage, would be an impressive room Authorized for use only by Ishiga Pail in OPER3P92 at Brock University from 9/5/2023 to 12/24/2023 with state-of-the-art multimedia capabilities and intricate millwork. On September 24, Cage Drywall was in the process of hanging and finishing the drywall in the sanctuary. At the time of the last report, the company estimated that it would take 16 additional days. For planning purposes, Grott divided the sanctuary into three main areas; the auditorium seating. the bowl and the terrace. Use outside th Work on the auditorium seating was in its final stages. The core drill for the rails would take an additional two days before it was complete. Once this was finished, the rails would be installed along with carpeting at the seats. Grott estimated that these tasks could take five and 15 days, respectively. Carpeting at the rails would take five days but could only be started once the rails were installed and the wood panelling, trim and stage work was completed, which would take 25 days and could be started following the installation of carpet in the seating area. Painting could occur once the concrete floor in the bowl area was stained, the stage steps were carpeted and the carpet at the seats was completed, and was estimated to be finished within 20 days. The final step in completing the risers was installing the seats: this required approximately 20 days, and would be started upon completion of the wood panelling, trim and stage flooring work and the scat installation in the bowl area. Grott and his team used the term "bowl" to refer to the sanctuary area that was flat; in other words, the area directly in front of the stage that did not include the sloped portion. Installation of the seats in this area was scheduled to begin immediately following completion of the drywall: it was expected to take 20 days. Some of the concrete floor in this area needed to be stained and would take five days to finish, but this could begin only after the wood stage steps were completed. The steps would be started after the core drill for the rails was completed and would also take five days. In parallel to staining the concrete floor, carpet installation in the other sections of the bowl area could begin. Grott expected the subcontractor to take approximately five days to install carpet at the stage steps, flats and aisles. In the sanctuary, the crew would install the doors andPage 6 9810D016 hardware when the painting, wood panelling, trim and stage flooring work were finished. Again, this task could take from five to eight days, as Hawker previously explained for the bookstore arca. The architect designed a terrace just outside of the sanctuary. The window surrounds of the terrace were already under construction on September 24, and would take approximately eight days to be completed. The next task, which would take seven days, was waterproofing the terrace. As Grott continued reviewing the tasks with his team, he indicated that insulation would take three days, and could be started after waterproofing the terrace. Hawker explained the work on the concrete deck and stairs on the terrace; following insulation, the crew would pour concrete for the deck. There was large variability in this task, as progress in laying concrete is affected by the weather conditions. He expected the crew to take anywhere from 5-10 days to complete the deck. The stairs could be poured after the deck was finished. Because they take more time and attention, the stairs were scheduled to take 10 days, however, Hawker's crew was known for their dedication and hard work, and could greatly reduce this time with overtime on wecknights and weekends. At the same time that the stairs were being poured, aluminum rails would be installed. The rails would take five days to complete. The final task for the terrace was completing the masonry on the stairs. Southern States Masonry Inc. was contracted to do all bricklaying work for the project, and as Brodbeck explained, they were scheduled to come in at completion of the concrete stairs and railings and were expected to take 10 days. Construction of the sanctuary would be officially finished at this time and would be followed, as with the other two sections, by cleaning and preparation of the ACI punch list. copyright violation DEVELOPING THE PLAN Grott and the team were beginning to notice that without overtime work and incentives for the Authorized for use only by Ishiga Pail in OPER3P92 at Brock University from 9/5/2023 to 12/24/2023. subcontractors to work faster, the project may not be completed on time. In addition, there was no room in the timeline for errors or mistakes, which would inevitably occur. Grott still had a few hours before he was planning to meet with the architects and the client, since he wanted to be confident in this meeting that the job would be done on time, he needed to work diligently to arrive at a solution. Grott excused everyone on the team except for Brodbeck and Hawker. Use outside The team knew how important it was to have the expansion completed by December 14 if they were to maintain the reputation of ACT and preserve future opportunities for the company. They began to work on the currently proposed schedule, hoping to be able to bring good news to that afternoon's meeting

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Introduction To Management Science

Authors: Bernard W. Taylor

13th Edition

0134730666, 978-0134730660

More Books

Students also viewed these General Management questions

Question

Always have the dignity of the other or others as a backdrop.

Answered: 1 week ago