Team Folklore has just completed Sprint 1 and now needs to schedule their planning meeting for Sprint 2. When should they schedule their sprint planning
Team Folklore has just completed Sprint 1 and now needs to schedule their planning meeting for Sprint 2. When should they schedule their sprint planning meeting for Sprint 2?
-
Before Sprint 2 begins
-
During the middle of Sprint 1
-
At the end of Sprint 2