Technique used to reduce the project's overall duration by identifying activities on the critical path that were connected in serial, but can be performed in
Technique used to reduce the project's overall duration by identifying activities on the critical path that were connected in serial, but can be performed in parallel, thus reducing the duration of that path. Group of answer choices expediting fast-tracking schedule crashing critical chain method