tements The manager of a crew that installs carpeting has tracked the crew's output over the past several weeks. For the given information, what is
tements The manager of a crew that installs carpeting has tracked the crew's output over the past several weeks. For the given information, what is the labor productivity in Week 2 in terms of the yards installed per person? (Enter your response rounded to two decimal places.) Week 1 2 3 4 5 6 Crew Size 4 3 4 2 3 2 Yards Installed 97 69 97 52 66 52 Labor Productivity (Yards/Person) ? Question Time Elapsed: H Attempt due: Jun 5 at: O Minutes, 19 Seco