Temporary Housing Services Incorporated (THSI) is considering a project that involves setting up a temporary housing facility in an area recently damaged by a hurricane.

Temporary Housing Services Incorporated (THSI) is considering a project that involves setting up a temporary housing facility in an area recently damaged by a hurricane. THSI will lease space in this facility to various agencies and groups providing relief services to the area. THSI estimates that this project will initially cost $4 million to set up and will generate $23 million in revenues during its first and only year in operation (paid in one year). Operating expenses are expected to total $8 million during this year and depreciation expense will be another $4 million. THSI will require no working capital for this investment. THSI's tax-rate is 20%

Assume that THSI's cost of capital for this project is 15%. The net present value (NPV) of this temporary housing project is closest to:

A. $13

B. $7,130,435

C. $14,260,870

D. $7,130,435

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Personal Finance

Authors: Jack Kapoor, Les Dlabay, Robert J Hughes

9th Edition

0073382329, 9780073382326

More Books

Students also viewed these Finance questions

Question

Why is rejecting ????0 a reliable decision?

Answered: 1 week ago

Question

2. Find five metaphors for communication.

Answered: 1 week ago