Tessa is applying an adaptive life cycle for the project she is leading. How should she plan the project activities? Develop a high-level plan as
Tessa is applying an adaptive life cycle for the project she is leading. How should she plan the project activities? Develop a high-level plan as the project progresses. Plan all of the iterations' work before the start of the project. Progressively elaborate the scope based on continuous feedback. Execute the project activities described in the statement of work