Thane Company is interested in establishing the relationship between electricity costs and machine hours. Data have been collected and a regression analysis prepared using Excel.
Thane Company is interested in establishing the relationship between electricity costs and machine hours. Data have been collected and a regression analysis prepared using Excel. The monthly data and the regression output follow:
Month | Machine Hours | Electricity Costs | ||
January | 2,600 | $ | 18,450 | |
February | 3,000 | $ | 21,100 | |
March | 2,000 | $ | 13,550 | |
April | 3,200 | $ | 23,100 | |
May | 3,900 | $ | 28,300 | |
June | 3,400 | $ | 22,100 | |
July | 4,200 | $ | 24,800 | |
August | 3,600 | $ | 22,800 | |
September | 2,100 | $ | 15,600 | |
October | 3,800 | $ | 26,100 | |
November | 4,800 | $ | 31,100 | |
December | 4,300 | $ | 27,800 | |
Summary Output | |
Regression Statistics | |
Multiple R | 0.965 |
R Square | 0.931 |
Adjusted R2 | 0.924 |
Standard Error | 1,433.89 |
Observations | 12.00 |
Coefficients | Standard Error | t Stat | P-value | Lower 95% | Upper 95% | |
Intercept | 3,227.67 | 1,741.27 | 1.85 | 0.09 | (652.13) | 7,107.46 |
Machine Hours | 5.77 | 0.50 | 11.63 | 0.00 | 4.67 | 6.88 |
If the controller uses regression analysis to estimate costs, the estimate of the fixed portion of electricity costs is:
Multiple Choice
-
Fixed Cost = $5.77.
-
Fixed Cost = $1,741.27.
-
Fixed Cost = $1,433.89.
-
Fixed Cost = $3,227.67.
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started