Question
The 195 Factory produces replacement parts and assemblies for vintage Cessna aircraft. The company is considering replacing its current costing system with an activity-based approach.
The 195 Factory produces replacement parts and assemblies for vintage Cessna aircraft. The company is considering replacing its current costing system with an activity-based approach. It has identified three activities: computer-aided design; fabrication; and assembly and finishing. Data regarding these activities has been collected in the table below.
Activity | Driver | Driver Frequency | Activity Cost |
Computer-aided design (CAD) | (CAD) hours | 2,000 | $1,000,000 |
Fabricating | Machine hours | 2,000 | $600,000 |
Assembly and finishing | Labor hours | 8,000 | $400,000 |
(A) What is the activity cost rate for the computer-aided design activity?
(B) Two jobs are currently complete and ready for delivery to the customer. One is a wing assembly that required raw materials costing $5,000 and consumed 40 hours of direct labor time. The wing assembly is a standard product that required only one hour of CAD time and three hours of machine time. What amount of overhead would the proposed activity-based costing system assign to this job?
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started