Answered step by step
Verified Expert Solution
Question
1 Approved Answer
The _ _ _ _ _ _ _ _ _ _ _ _ _ technique is used to estimate project duration when there is a
Thetechnique is used to estimate project duration when there is a high degree of uncertainty about the individual activity duration estimates. This technique uses 'probabilistic time estimates'duration estimates based on using optimistic, most likely, and pessimistic estimates of activity durations rather than one specific or discrete duration estimate.
Question options:
program evaluation and review PERT
critical path method
time series
Gantt chart
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started