The 8th unit of a 13-unit job took eight hours to complete. The 9th unit has been worked on for four hours but is not

The 8th unit of a 13-unit job took eight hours to complete. The 9th unit has been worked on for four hours but is not yet finished. Use the following table for calculation. Learning curve coefficients

70% 75% 80% 85% 90%
Unit Number Unit Time Total Time Unit Time Total Time Unit Time Total Time Unit Time Total Time Unit Time Total Time
1 1.000 1.000 1.000 1.000 1.000 1.000 1.000 1.000 1.000 1.000
2 0.700 1.700 0.750 1.750 0.800 1.800 0.850 1.850 0.900 1.900
3 0.568 2.268 0.634 2.384 0.702 2.502 0.773 2.623 0.846 2.746
4 0.490 2.758 0.562 2.946 0.640 3.142 0.723 3.345 0.810 3.556
5 0.437 3.195 0.513 3.459 0.596 3.738 0.686 4.031 0.783 4.339
6 0.398 3.593 0.475 3.934 0.562 4.299 0.657 4.688 0.762 5.101
7 0.367 3.960 0.446 4.380 0.534 4.834 0.634 5.322 0.744 5.845
8 0.343 4.303 0.422 4.802 0.512 5.346 0.614 5.936 0.729 6.574
9 0.323 4.626 0.402 5.204 0.493 5.839 0.597 6.533 0.716 7.290
10 0.306 4.932 0.385 5.589 0.477 6.315 0.583 7.116 0.705 7.994
11 0.291 5.223 0.370 5.958 0.462 6.777 0.570 7.686 0.695 8.689
12 0.278 5.501 0.357 6.315 0.449 7.227 0.558 8.244 0.685 9.374
13 0.267 5.769 0.345 6.660 0.438 7.665 0.548 8.792 0.677 10.052
14 0.257 6.026 0.334 6.994 0.428 8.092 0.539 9.331 0.670 10.721
15 0.248 6.274 0.325 7.319 0.418 8.511 0.530 9.861 0.663 11.384
16 0.240 6.514 0.316 7.635 0.410 8.920 0.522 10.383 0.656 12.040
17 0.233 6.747 0.309 7.944 0.402 9.322 0.515 10.898 0.650 12.690
18 0.226 6.973 0.301 8.245 0.394 9.716 0.508 11.405 0.644 13.334
19 0.220 7.192 0.295 8.540 0.388 10.104 0.501 11.907 0.639 13.974
20 0.214 7.407 0.288 8.828 0.381 10.485 0.495 12.402 0.634 14.608
21 0.209 7.615 0.283 9.111 0.375 10.860 0.490 12.892 0.630 15.237
22 0.204 7.819 0.277 9.388 0.370 11.230 0.484 13.376 0.625 15.862
23 0.199 8.018 0.272 9.660 0.364 11.594 0.479 13.856 0.621 16.483
24 0.195 8.213 0.267 9.928 0.359 11.954 0.475 14.331 0.617 17.100
25 0.191 8.404 0.263 10.191 0.355 12.309 0.470 14.801 0.613 17.713
26 0.187 8.591 0.259 10.449 0.350 12.659 0.466 15.267 0.609 18.323
27 0.183 8.774 0.255 10.704 0.346 13.005 0.462 15.728 0.606 18.929
28 0.180 8.954 0.251 10.955 0.342 13.347 0.458 16.186 0.603 19.531
29 0.177 9.131 0.247 11.202 0.338 13.685 0.454 16.640 0.599 20.131
30 0.174 9.305 0.244 11.446 0.335 14.020 0.450 17.091 0.596 20.727

Estimate the additional amount of time needed to finish the 13-unit job if the work has a 75 percent learning rate. (Round your intermediate calculations and final answer to 3 decimal places.)

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image_2

Step: 3

blur-text-image_3

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Business Research Methods

Authors: Alan Bryman, Emma Bell

3rd Edition

0199583404, 9780199583409

More Books

Students also viewed these General Management questions

Question

14. Now reconcile what you answered to problem 15 with problem 13.

Answered: 1 week ago