The Ace Tool Company is considering implementing transfer batches in scheduling the firms fabrication shop i.e. once 100 units have been processed in Work Centre
The Ace Tool Company is considering implementing transfer batches in scheduling the firm’s fabrication shop i.e. once 100 units have been processed in Work Centre 1, they are transferred to Work Centre 2. The production manager selected an example order to use in evaluating benefits and potential costs of this scheduling approach. A transfer batch size of 100 units was suggested for this item. The example order is for a quantity of 1000 units and has the following routing data.
|
Assuming a single shift, 8 hour day, 5 day week for work centers 1 and 2.
Q 1 (i) Prepare a Gantt Chart showing the earliest start and finish schedule for this order under a conventional scheduling approach when all 1000 units are processed together in one batch. Compare this to a Gantt Chart showing when batch sizes of 100 are used (assume one setup in Work Centre 2 is sufficient for all batches). You will obviously need to calculate the time spent in the work Centre's etc. so remember to show you’re mathematical workings as well as the Gantt Chart.
Q 1 (ii) What are the advantages of using the batch transfer system?
Step by Step Solution
3.56 Rating (156 Votes )
There are 3 Steps involved in it
Step: 1
The question is complete Ill just proceed with the answer Q1 i Firstly lets calculate the time spent for each case Case 1 1000 units in one batch Set ...Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started