Question: The activities described by the following table are given for the Howdie Corporation: Activity Immediate Predecessors Time A - 9 B A 7 C A

The activities described by the following table are given for the Howdie Corporation:
Activity Immediate Predecessors Time
A - 9
B A 7
C A 3
D B 6
E B 9
F C 4
G E, F 6
H D 5
I G, H 3
By using the CPM analysis technique, find the critical path and the project completion time.
(