The activities, immediate predecessors and time required for a project are shown in below: IMMEDIATE PREDECESSOR ( S ) ACTIVITY A B D E F

The activities, immediate predecessors and time required for a project are shown in below:
IMMEDIATE PREDECESSOR (S)
ACTIVITY
A
B
D
E
F
G
H
A,B
B
C
E,F
TIME (MONTHS)
3
5
3
3
2
1
3
2
i. Draw the precedent diagram.
ii. Calculate Earliest Finish and Latest Start based on the precedent diagram above.
iii. By using the information in question 1(b), identify the critical path.
iv. By using the information in question 1(b), determine the project completion time.
v. If activity C were delayed by 2 months, what would be the impact on the project completion? Explain your answer.

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Project Management The Managerial Process

Authors: Erik Larson, Clifford Gray

6th edition

1259186407, 978-0078096594, 78096596, 978-1259186400

More Books

Students also viewed these General Management questions