The activity involved in a certain project have been identified as follows: Job Time ( weeks ) No . of Men required Precedence requirements A
The activity involved in a certain project have been identified as follows:
Job Time
weeks
No of Men
required
Precedence
requirements
A
B A
C A
D BC
E BC
F E
G DF
H G
a For the above project draw the network using the MS word line function and
determine the critical path.
b If there are three men available at any one time how long would the project take
and how would you allocate the men to the activities?
c If there are no restrictions on the amount of labour available, explain how you
would schedule the activities? marks
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started