Answered step by step
Verified Expert Solution
Link Copied!

Question

1 Approved Answer

The Advanced Tech Company has a project to design an integrated information data base for a major bank. Data for the project are given

image text in transcribedimage text in transcribedimage text in transcribedimage text in transcribed

The Advanced Tech Company has a project to design an integrated information data base for a major bank. Data for the project are given in the following table. Indirect project costs amount to $250 per day. The company will incur a $100 per day penalty for each day the project lasts beyond day 20. a. What is the project's duration if only normal times are used? Normal Time Crash Time Crash Cost Activity Normal Cost ($) (days) (days) ($) Immediate Predecessor(s) A 6 800 3 2,000 B 5 1,000 3 1,200 C 5 500 3 1,500 A, B D 3 1,200 2 1,500 B E 5 1,500 2 2,100 C, D F 3 1,300 1 1,400 E G 4 900 3 1,000 E H 5 500 5 500 G The project duration is day(s). (Enter your response as an integer.) b. What is the minimum-cost schedule? With the minimum-cost schedule, the project duration is day(s) (Enter your response as an integer.) c. What is the critical path for the minimum-cost schedule? The critical path for the minimum-cost schedule is Recently, you were assigned to manage a project for your company. You have constructed a network diagram depicting the various activities in the project (shown below to the right). In addition, you have asked your team to estimate the amount of time that they would expect each of the activities to take. Their responses are shown in the following table: Time Estimates (days) Activity Optimistic Most Likely Pessimistic A 5 7 10 B 3 9 11 Start Finish C 5 7 8 D 2 3 6 B E E 3 8 10 a. What is the expected completion time of the project? The expected completion time is days. (Enter your response as an integer.) Q a. What is the expected completion time of the project? The expected completion time is days. (Enter your response as an integer.) b. What is the probability of completing the project in 20 days? Refer to the standard normal table. The probability of completing the project in 20 days is (Enter your response rounded to four decimal places.) c. What is the probability of completing the project in 16 days? The probability of completing the project in 16 days is (Enter your response rounded to four decimal places.)

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access with AI-Powered Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Operations Management Processes and Supply Chains

Authors: Lee J. Krajewski, Larry P. Ritzman, Manoj K. Malhotra

10th edition

978-0132807395

More Books

Students also viewed these General Management questions

Question

Do Bill and Melinda Gates have an LMP? Compare the two.

Answered: 1 week ago

Question

How do we solve traveling salesman problem with genetic algorithms?

Answered: 1 week ago

Question

What are Lissajous patterns?

Answered: 1 week ago

Question

How do we measure non-sinusoidal waveforms?

Answered: 1 week ago

Question

What are the different types of packages used in Computer Science?

Answered: 1 week ago

Question

Rules in accounting

Answered: 1 week ago

Question

2. Estimate the gains and costs of mergers to the acquiring firm.

Answered: 1 week ago