The advanced tech company has a project to design an integrated information data base for a major bank. Data for the project are given in

The advanced tech company has a project to design an integrated information data base for a major bank. Data for the project are given in the following table. Indirect project costs amount to $150 per day. the company will incur a $ 100 per daypenalty for each dayproject lasts beyond day 18 .

Activity Normal Time (days) Normal Cost ($) Crash Time (days) Crash Cost ($) Immediate Predecessor(s)
A 5 800 3 1,600 -
B 4 1,000 3 1,200 -
C 4 600 3 900 A, B
D 3 1,200 2 1,500 B
E 4 1,500 2 1,700 C, D
F 2 1,300 1 1,400 E
G 5 900 3 1,200 E
H 5 500 5 500

G

A- what is the projects duration if only normal times are used?

The prohect durations is 23 days and the critical path is A,C,E,G,H

B- WHAT IS THE MINUMUM COST SCEDUELE?

with the minimum-cost schedule, the project duration is ........... days

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Foundations Of Financial Markets And Institutions

Authors: Franco Modigliani, Frank J. Jones, Michael G. Ferri, Frank J. Fabozzi

3rd Edition

0130180793, 978-0130180797

More Books

Students also viewed these Finance questions

Question

What is a verb?

Answered: 1 week ago