The Analytic Hierarchy Process (AHP) is being employed in a project selection decision of three projects A, B, and C. The total score for project
The Analytic Hierarchy Process (AHP) is being employed in a project selection decision of three projects A, B, and C. The total score for project A is 0.650; for project B is 0.514; and for project C is 0.321. Which of the following statements is best?
1. Project A is as good as project C.
2. The analysis must be incorrect because the total scores must sum to 1.00.
3. The analysis must be incorrect because two total scores exceed 0.50.
4. The analysis must be incorrect because the Project C's score is odd.
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started