The Analytic Hierarchy Process (AHP) is being employed in a project selection decision of three projects A, B, and C. The total score for project

The Analytic Hierarchy Process (AHP) is being employed in a project selection decision of three projects A, B, and C. The total score for project A is 0.650; for project B is 0.514; and for project C is 0.321. Which of the following statements is best?

1. Project A is as good as project C.

2. The analysis must be incorrect because the total scores must sum to 1.00.

3. The analysis must be incorrect because two total scores exceed 0.50.

4. The analysis must be incorrect because the Project C's score is odd.

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Operations And Supply Chain Management

Authors: David A. Collier, James R. Evans

2nd Edition

035713169X, 978-0357131695

More Books

Students also viewed these General Management questions

Question

What approach(es) to psychotherapy do you prefer?

Answered: 1 week ago

Question

How easy the information is to remember

Answered: 1 week ago

Question

The personal characteristics of the sender

Answered: 1 week ago

Question

The quality of the argumentation

Answered: 1 week ago