Question

00
1 Approved Answer

The AON diagram shown represents a project. Normal and crash times, and the associated costs, are shown for each activity in the accompanying table. The

The AON diagram shown represents a project. Normal and crash times, and the associated costs, are shown for each activity in the accompanying table. The project duration should be shorten one day. Which activity should be crashed one day?

Activity

Normal Time (days)

Crash Time (days)

Normal Cost ($)

Crash Cost ($)

1

Start

Start

-

-

2

2

1

9100

17400

3

3

1

14500

19300

4

4

2

20400

27500

5

5

5

19700

19700

6

6

3

5700

14900

7

6

4

8020

17600

8

6

4

10400

25300

9

End

End

-

-

Question 21Answer

a.1

b.2

c.3

d.4

e.5

f.6

g.7

h.8

i.None of them. It is impossible to crash the project.

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access with AI-Powered Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Entrepreneurship

Authors: Andrew Zacharakis, William D Bygrave

5th Edition

1119563097, 9781119563099

Students also viewed these General Management questions