The AON diagram shown represents a project. Normal and crash times, and the associated costs, are shown for each activity in the accompanying table. The
The AON diagram shown represents a project. Normal and crash times, and the associated costs, are shown for each activity in the accompanying table. The project duration should be shorten one day. Which activity should be crashed one day?
Activity | Normal Time (days) | Crash Time (days) | Normal Cost ($) | Crash Cost ($) |
1 | Start | Start | - | - |
2 | 2 | 1 | 9100 | 17400 |
3 | 3 | 1 | 14500 | 19300 |
4 | 4 | 2 | 20400 | 27500 |
5 | 5 | 5 | 19700 | 19700 |
6 | 6 | 3 | 5700 | 14900 |
7 | 6 | 4 | 8020 | 17600 |
8 | 6 | 4 | 10400 | 25300 |
9 | End | End | - | - |
Question 21Answer
a.1
b.2
c.3
d.4
e.5
f.6
g.7
h.8
i.None of them. It is impossible to crash the project.
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started