The Armer Company is accumulating data to be used in preparing its annual profit plan for the coming year. The cost behavior pattern of the
The Armer Company is accumulating data to be used in preparing its annual profit plan for the coming year. The cost behavior pattern of the maintenance costs must be determined. The accounting staff has suggested that linear regression be employed to derive an equation in the form of y = a + bx for maintenance costs. Data regarding the maintenance hours and costs for last year and the results of the regression analysis are as follows: (CMA adapted)
Hours of Activity | Maintenance Costs | |||||||
January | 480 | $ | 4,200 | |||||
February | 320 | 3,000 | ||||||
March | 400 | 3,600 | ||||||
April | 300 | 2,820 | ||||||
May | 500 | 4,350 | ||||||
June | 310 | 2,960 | ||||||
July | 320 | 3,030 | ||||||
August | 520 | 4,470 | ||||||
September | 490 | 4,260 | ||||||
October | 470 | 4,050 | ||||||
November | 350 | 3,300 | ||||||
December | 340 | 3,160 | ||||||
Sum | 4,800 | $ | 43,200 | |||||
Average | 400 | 3,600 | ||||||
A coefficient | 684.65 | |||||||
B coefficient | 7.2884 | |||||||
Standard error of the a coefficient | 49.515 | |||||||
Standard error of the b coefficient | 0.12126 | |||||||
Standard error of the estimate | 34.469 | |||||||
R2 | 0.99724 | |||||||
T-value a | 13.827 | |||||||
T-value b | 60.105 | |||||||
Using the high-low method to estimate cost behavior, 420 maintenance hours in a month would mean the maintenance costs would be budgeted at
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started