The assembly line for a music system of cars has the activities as mentioned in the table below for a demand of 1 2 0

The assembly line for a music system of cars has the activities as mentioned in the table below for a demand of 120 systems per day with 8 hours of production time per day. You are supposed to determine
a. Draw the precedence graph.
b. What is the cycle time?
c. Theoretically, how many number of workstations are required?
d. Assign the tasks to the workstations?
e. Based on the number of workstations in (d), what is the efficiency and the idle time?
image text in transcribed

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image_2

Step: 3

blur-text-image_3

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Management Information Systems

Authors: Jane Price Laudon, Ken Laudon

11th Edition

013607846X, 9780136078463

Students also viewed these General Management questions