The avoid risk strategy could involve which of the following. Group of answer choices Eliminating the cause
Fantastic news! We've Found the answer you've been seeking!
Question:
The avoid risk strategy could involve which of the following.
Group of answer choices
Eliminating the cause of the risk
Changing or relaxing the project objective that is at jeopardy
Documenting the strategy
Implementing and monitoring the avoid strategy planned
Change the project management plan to avoid the risk