The AW values of three independent projects are $-1,000 for alternative A, +$12,600 for B, and +$5,000 for C. On the basis of these results,
The AW values of three independent projects are $-1,000 for alternative A, +$12,600 for B, and +$5,000 for C. On the basis of these results, the decision is to:
Question 21 options:
Select alternative A only | |
Select alternative B only | |
Select alternative C only | |
Select alternatives B and C |