The below info is in regards to direct labor at a manufacturer of skateboards. Original estimate of skateboards 1000 Budgeted direct labor cost $30,400 Actual
The below info is in regards to direct labor at a manufacturer of skateboards.
Original estimate of skateboards
1000
Budgeted direct labor cost
$30,400
Actual number of skateboards produced
1050
Actual number of direct labor hours
860
Budgeted price of direct labor per hour
$38.00 per hour
Direct labor rate variance
$2,150 favorable
A) Which is the standard number of direct labor hours per skateboard
B) How much was actually spent on direct labor
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started