The below MRP table will appear at the beginning of week one. Lead time is 2 weeks and the lot size is 1 0 0

The below MRP table will appear at the beginning of week one. Lead time is 2 weeks and the lot size is 100 units.
Initial MRP
\table[[Week,1,2,3,4],[Gross requirements,70,40,80,50],[Scheduled receipts,100,,,],[Projected available,80,40,60,10],[Net requirements,,,40,],[Planned order receipt,,,100,],[Planned order release,100,,100,]]
During week one, the following events occur.
The gross requirements of 70 in week one are issued
The planned order for 100 in week one is released and becomes a scheduled receipt in
Twenty of the scheduled receipts for week one are scrapped
An order for 40 is received for delivery in week 3
Complete the following partial MRP record at the end of week one
\table[[Week,2,3,4],[Gross requirements GR,40,dotsdots-,50],[Scheduled receipts SR,,dotsdots-,],[Projected available PA,20,20,dotsdots-.-
image text in transcribed

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Wiley CIA Essentials Of Internal Auditing Exam Review 2022 Part 1

Authors: S. Rao Vallabhaneni

1st Edition

1119846285, 978-1119846284

More Books

Students also viewed these Accounting questions

Question

Describe the nature of negative messages.

Answered: 1 week ago