The Bienestar Cardiology Clinic has two major activities: diagnostic and treatment. The two activities use four resources: nursing medical technicians, cardiologists, and equipment. Detailed interviews have provided the work distribution matrix shown. Resources Total Activity Activity Nursing Technicians Cardiologists Equipment Time Diagnosing patients 0.70 0.80 0.40 0.60 12,000 hrs. Treating patients 0.30 0.20 0.60 0.40 8,000 hrs. Total time (hrs.) 4.000 4.000 6.000 6,000 20,000 Cost $80,000 $80,000 $320,000 $320,000 The total time estimated corresponds to practical capacity (interviewers adjusted the total time to about 80 percent of the available time). The equipment time is measured in machine hours. Thus, the total time (at practical capacity) in the system is 20,000 hours. In considering the implementation of a TDABC model, the following unit times and transaction information are also provided: Unit Expected Activity Time Driver Driver Quantity Diagnosing patients 3 hrs. No. of patients 4.000 Treating patients 0.8 hr. No. of treatments 10,000Required: 1. Calculate the cost of each activity using the indicated values of the resource drivers. 2. Calculate the capacity cost rate for TDABC. Using the capacity cost rate, calculate the cost of each activity under TDABC. Compare these values with those obtained in Requirement 1 and discuss possible reasons for any differences. 3. Suppose that the actual activity driver quantities are 3,500 and 9,000. Calculate the cost of unused capacity. Answer + Check Figures: Unused capacity cost = $92,000 4. Suppose that the clinic acquires new equipment that reduces the total time required for the two activities from 6,000 to 4,000 hours. The equipment cost remains the same. Explain how the ABC system would be updated and then describe how TDABC would provide updates. 5. Suppose that diagnosing patients without any cardiac disease takes two hours while diagnosing patients with mildly diseased hearts takes an additional 1.5 hours and those with more severe problems takes an additional two hours. Prepare a time equation and, using the capacity cost rate from Requirement 2, calculate the activity rate for each of the three types of patients