Question
The Bloomington Bike Company produces two models: the Basic (B) and the Supra (S). Herb Hoosier, the owner, plans to assemble 24 Basics and 18
The Bloomington Bike Company produces two models: the Basic (B) and the Supra (S). Herb Hoosier, the owner, plans to assemble 24 Basics and 18 Supras in each week during periods 6 to 8. Product structure trees for each bike are shown below:
Data on all lead times, current inventory and ordering rules are given below. Suppose there are no schedule receipts. Develop a materials requirement plan for component parts K and W over the next 8 weeks.
ITEM | LEADTIME (WKS) | ON HAND | LOT-SIZING RULE |
B | 2 | 5 | Lot-for-lot |
S | 2 | 2 | Multiples of 15 |
X | 1 | 5 | Multiples of 25 |
W | 2 | 0 | Multiples of 12 |
F | 1 | 0 | Lot-for-lot |
K | 1 | 3 | Multiples of 20 |
Q | 1 | 15 | Multiples of 30 |
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started