The board of directors of Sheridan Construction Company is meeting to choose between the completed-contract method and the percentage-of-completion method of accounting for long-term contracts

The board of directors of Sheridan Construction Company is meeting to choose between the completed-contract method and the percentage-of-completion method of accounting for long-term contracts in the company's financial statements. You have been engaged to assist Sheridan's controller in the preparation of a presentation to be given at the board meeting. The controller provides you with the following information:

1.Sheridan commenced doing business on January 1, 2021.
2.Construction activities for the year ended December 31, 2021, were as follows:
ProjectTotal Contract
Price
Billings Through
12/31/21
Cash Collections
Through 12/31/21
Contract Costs
Incurred Through
12/31/21
Estimated
Additional Costs to
Complete Contracts
A$ 495,000$ 335,000$ 305,000$ 419,000$ 96,000
B715,000205,000205,000187,500437,500
C472,500470,000385,000345,000-0-
D197,50095,00062,500118,00092,000
E445,000395,000395,000315,00078,750
$2,325,000$1,500,000$1,352,500$1,384,500$704,250
3.Each contract is with a different customer.
4.Any work remaining to be done on the contracts is expected to be completed in 2022.
Compute the amount of income (or loss) before selling, general, and administrative expenses for the year ended December 31, 2021, which would be reported under:
(1)The completed-contract method.$

(2)The percentage-of-completion method (based on estimated costs).$

SHOW LIST OF ACCOUNTS

Prepare the general journal entry to record revenue and gross profit on project B (second project) for 2021, assuming that the percentage-of-completion method is used. (Credit account titles are automatically indented when amount is entered. Do not indent manually. If no entry is required, select "No Entry" for the account titles and enter 0 for the amounts.)

Account Titles and Explanation

Debit

Credit

SHOW LIST OF ACCOUNTS

Indicate the balances that would appear in the balance sheet at December 31, 2021 for the following accounts for Project D (fourth project), assuming that the percentage-of-completion method is used.
Accounts Receivable$

Billings on Construction in Process$

Construction in Process$

SHOW LIST OF ACCOUNTS

How would the balances in the accounts discussed in part (c) change (if at all) for Project D (fourth project), if the completed-contract method is used?
If the completed-contract method is used the account balances

would increasewould decreasewould be the same

.

Step by Step Solution

3.47 Rating (163 Votes )

There are 3 Steps involved in it

Step: 1

To assist Sheridan Construction Companys controller in the preparation of the presentation I will provide the requested information and calculations L... blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Financial and Managerial Accounting

Authors: Horngren, Harrison, Oliver

3rd Edition

978-0132497992, 132913771, 132497972, 132497999, 9780132913775, 978-0132497978

More Books

Students also viewed these Accounting questions