Question

1 Approved Answer

The Bolton Construction Company is preparing a bid to build the new 56,000 seat Commonwealth Stadium in Toronto. The construction must start September 4, 2021

The Bolton Construction Company is preparing a bid to build the new 56,000 seat Commonwealth Stadium in Toronto. The construction must start September 4, 2021 and be completed in time for the 2024 Commonwealth Games. The contract contains a penalty clause of $100,000.00 per day of delay beyond June 1st, 2024. At a recent management meeting Charlie Musselman, the president of the company, expressed optimism at winning the contract and revealed that the company could net as much as $2 million on the project. He also said that if they are successful, the prospects for future projects are quite good since there are quite a few major stadiums in Canada that will need replacing in the next 25 years.

Part One Given the information provided in the Technical Detail Description of the project, hand draw a network information chart and an AON network diagram and then answer the following questions: (10 Points)

1. Will the project be completed by the June 1st project deadline?

2. How long will the project take?

3. What is (are) the critical path(s) of the project.

4. Should the company accept the contract if they win the bid?

Technical Detail Description The Stadium is an outdoor structure with a retractable roof. The project begins with clearing the site (70 days.). Once the site is clear, work can start simultaneously on demolishing an adjacent building (20 days), and setting up the construction site (50 days). This demolition is necessary to create a temporary warehouse (30 days) for seating, lighting and infrastructure materials. The work on the stadium begins by driving 160 support pilings (120 days). Next comes the pouring of the lower concrete bowl (120 days). Then the pouring of the main concourse (120 days), the installation of the playing field (90 days), and the construction of the upper steel bowl (120 days) can proceed in parallel, not in sequence. After the concourse, upper bowl and temporary construction storage area are completed, work can start simultaneously on installing the seats (140 days), building the luxury boxes (90 days), installing the Jumbo Scoreboard (30 days), and installing the stadium infrastructure (120 days) which includes: bathrooms, lockers, restaurants, dressing rooms, media rooms, etc. Once the seats are installed then the steel canopy can be constructed (75 days) followed by the installation of the lighting and sound systems (30 days). The retractable roof represents the most significant technical challenge to the project. Building the roof track supports (80 days) can begin after the lower concrete bowl is constructed. After this, confirmation of the dimensions of the roof (10 days) can be finalized and the construction of the roof (180 days) at a separate site can begin. After the roof supports are completed then the roof tracks can be installed (90 days). Once the tracks and the roof are completed, then the roof can be trucked in (5 days), and roof tracks installed (90 days). Finally, the roof will be installed (90 days). After all the construction activities are completed, the stadium will be ready for inspection (20 days.)

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Analysis For Financial Management

Authors: Robert C. Higgins

12th International Edition

1260091910, 9781260091915

More Books

Students also viewed these Finance questions