The BOM for product Z is as follows: Master Production Schedule for Z Period 1 2 3 4 5 6 7 8 9 Gross Requirements
The BOM for product Z is as follows:
Master Production Schedule for Z
Period | 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 |
Gross Requirements |
|
|
| 30 |
| 20 |
| 40 | 25 |
Item | A | B | C | D | E |
Lead Time | 1 | 2 | 2 | 1 | 3 |
On-hand | 25 | 10 | 10 | 8 | 0 |
Lot Size | L4L | POQ = 3 | L4L | L4L | FOQ=20 |
Scheduled receipt | 60 (week 1) | (30 week 3) | 40 (week 2) | (60 week 2) | 240 (week 1) |
Prepare the MRP records for the components.