Question

1 Approved Answer

The brief construction plan for Apple Park which is in California, USA is as follows . Based on the below information write scope of the

The brief construction plan for Apple Park which is in California, USA is as follows . Based on the below information write scope of the project, in scope, out scope and WBS.

INTRODUCTION

This project epitomizes Apple Inc.'s unwavering commitment to innovation, sustainability, and efficiency. Located in the center of Silicon Valley, the expansion of Apple Park is an innovative project that combines state-of-the-art building techniques with innovative technologies. This development plan includes several innovative technologies to improve Apple Park's infrastructure and meet the company's changing needs. Every element, from 3D printing and Building Information Modelling (BIM) to drones and prefabrication, is carefully selected to improve the project's user experience, sustainability, and efficiency. This strategy aims to establish a campus that is not just operational but also a global leader in sustainability and innovation, utilizing cutting-edge technologies and sustainable practices.

SCHEDULE

Phase One: Site Preparation.

Duration: six months.

  1. Clearing and grading 175 acres.
  2. Excavating and earth moving.
  3. Implementation of erosion-control methods.

Phase Two: Infrastructure Development

Duration: twelve months

  1. Construction of roads and parking lots.
  2. Installation of utilities (water, sewer, electricity, and telecommunications).
  3. Integration of smart technologies to improve energy efficiency.

Phase Three: Architectural Construction

Duration: twenty-four months.

  1. Construction of the main office building and other important structures.
  2. Use of modern construction processes and materials.
  3. Interior fit-out and finish.

Phase Four: Landscape Design Duration: eighteen months

  1. The creation of green spaces and landscaping.
  2. Implementing sustainable landscaping principles.
  3. Integration of outdoor facilities.

Phase Five: Environmental Considerations Duration: ongoing while construction

  1. Continued use of eco-friendly materials and procedures.
  2. Monitoring and management of environmental impacts.

Phase Six: Technology Integration

Duration: twelve months

  1. Installation of modern technological infrastructure.
  2. Integrating security and communication systems.
  3. Testing and optimization of technological solutions.

Phase Seven: Project Management

Duration: during construction

  1. Complete project scheduling and coordination.
  2. Quality control and assurance measures.
  3. Regular stakeholder communication.

Phase Eight: Community Impact

Duration: during construction

  1. Ongoing involvement with the local community.
  2. Mitigating disruptions and addressing community concerns.

Phase Nine: Safety Measures

Duration: during construction

  1. Implementation and enforcement of safety protocols.
  2. Regular safety audits and training programs.

Phase Ten: Completion and Handover

Duration: three months

  1. Final inspections and quality checks.
  2. Coordination with Apple regarding occupancy and operational transitions.

In conclusion, the meticulously planned development timeline for Apple Park is intended to ensure the successful completion of this historic project. Each phase, from site preparation and infrastructure development to architectural building, landscape design, and technological integration, is carefully planned. The focus on environmental issues, community impact, and safety precautions demonstrates the project's commitment to excellence. As we near the end of this project, the project management team remains committed to on-time delivery, quality assurance, and a harmonious balance of innovation and sustainability that will establish Apple Park as an iconic landmark in the corporate world.

COST

The comprehensive analysis of Apple Park's building expenses covers several stages, including pre-construction tasks like surveys and feasibility studies, which is CAD 200,000. The installation of the facade and structural framework in the superstructure phase has cost around CAD 6 million. The MEP system installation has been done for CAD 7.5 million and safety precautions costing CAD 750,000 are included in the interior finishing. The CAD 600,000 in site preparation fees includes the price of excavation, grading, and demolition as well as site clearing. The entire cost of the foundation project, including concrete pouring and excavation, is CAD 3 million.

Apple Park Construction Cost Breakdown:

Phase Activity Labor Cost (CAD) Material Cost (CAD) Total Cost (CAD)
Pre-construction Feasibility Studies and Surveys $80,000 $120,000 $200,000
Permits and Approvals $320,000 $480,000 $800,000
Community Engagement $100,000 $150,000 $250,000
Legal and Consulting Fees $200,000 $300,000 $500,000
Site Preparation Demolition and Site Clearing $250,000 $250,000 $500,000
Grading and Excavation $375,000 $375,000 $750,000
Utility Hookups $300,000 $300,000 $600,000
Foundation Work Foundation Excavation $500,000 $500,000 $1,000,000
Footings and Piers $625,000 $625,000 $1,250,000
Foundation Concrete Pouring $750,000 $750,000 $1,500,000
Superstructure Structural Framing $1,250,000 $1.250.00
Facade Installation $1.750.00
Roofing $625.00

Total Estimated Cost: CAD 75 million

QUALITY:

The protocols, guidelines, and roles that must be followed to guarantee Apple Park World's construction is completed are described in the Construction Quality Plan. The objective of this plan is to attain construction excellence by upholding high standards, complying with pertinent regulations and specifications, and incorporating cutting-edge technologies.

Quality Plan:

Work Items Reference Documents Verification Activities

Responsible Parties

Characteristics and Measurements

Applicable Supporting Documentation

Foundation Construction

Structural Drawings, Building Codes

Soil Testing, Inspection

Civil Engineer

Depth, Strength, Alignment

Soil Test Reports, Inspection Reports

Modular Construction

Construction Drawings, Modular Assembly Plans

Assembly Inspection

Project Manager

Alignment, Fit, Finish

Assembly Inspection Reports

3D Printing

3D Printing Guidelines, Material Specifications

Prototype Testing

3D Printing Specialist

Dimensional Accuracy, Material Strength

Prototype Testing Reports

Drone Monitoring Drone Operation Guidelines, Flight Plans

Aerial Survey, Inspection

Drone Operator

Aerial Imagery Quality, Coverage

Aerial Survey Reports

Sustainable Materials

Green Building Standards, Material Certifications

Material Inspection

Sustainability Officer

Recycled Content, Sustainability Certificates

Material Inspection Reports

3 Quality Assurance Process:

1. Pre-Building Stage:

To guarantee accuracy, completeness, and compliance with legal requirements and project objectives, thoroughly review all design documents, including architectural drawings, engineering plans, and specifications.

Ensuring that all building materials are properly documented and certified and that they all adhere to the established standards and specifications, including sustainability requirements.

Make sure contractors and subcontractors have the knowledge and ability to fulfill project specifications and quality standards by assessing their credentials, experience, and performance history.

2. Construction phase:

To ensure adherence to design specifications, standards, and safety regulations, conduct routine inspections of construction activities, including foundation work, structural components, mechanical systems, and finishing work.

To confirm quality, strength, and durability as well as adherence to specifications, test, and sample building materials such as steel, concrete, and asphalt.

To provide a thorough audit trail and guarantee accountability, keep thorough records of all construction-related activities, inspections, test results, and any deviations or corrective measures implemented.

To ensure proper evaluation, approval, and communication of changes, implement a formal change management process to assess and document proposed changes to the construction scope, schedule, or specifications.

3. Post- Construction Phase:

Conduct a thorough final inspection of the finished construction to make sure that it complies with all legal requirements, quality standards, and design specifications. You should also look for any lingering problems or shortcomings.

Below list of items that need to be fixed or completed, then keep track of each item's progress to make sure that all issues are resolved to a high standard before the project is finished.

To guarantee appropriate functionality and performance and enable a seamless transition to the project's operational phase, coordinate the commissioning process for the mechanical, electrical, and plumbing systems.

4. Continuous Improvement:

Document lessons learned to guide future projects and improve quality management procedures. Conduct post-project reviews to identify successes, obstacles, and areas for improvement.

Give project team members continual opportunities for training and development to improve their abilities, knowledge, and comprehension of quality management techniques and cutting-edge technologies.

Establish feedback mechanisms, such as focus groups or surveys, to gather opinions from clients, contractors, and end users involved in the project. Then, integrate the feedback into efforts aimed at improving quality.

Through the implementation of comprehensive quality assurance protocols during the construction stages, the project team can guarantee that Apple Park World satisfies elevated benchmarks for quality, safety, and compliance, culminating in an advantageous and enduring consequence.

RESOURCES

Main Resources of the Project:

  1. Cutting-edge Digital Technologies: Utilizing Building Information Modeling (BIM), drones, prefabrication, 3D printing, IoT devices, RFID technology, and environmental monitoring systems.
  2. Sustainable Practices and Green Technologies: Incorporating solar electricity, green roofing, and sustainable materials.
  3. Strategic Partnerships: Establishing alliances with regional suppliers, companies, and academic institutions.
  4. Skilled Workforce: Engaging experienced professionals in construction, technology, project management, and sustainability.

Number of People:

The project will necessitate a diverse team of experts, including:

  • Project managers
  • Architects and designers
  • Engineers (civil, structural, mechanical, electrical)
  • Technicians (BIM, drone operators, 3D printing specialists)
  • Sustainability experts
  • IT professionals
  • Construction workers and laborers

Experience:

  • Project managers with a track record in overseeing large-scale construction projects and implementing advanced technologies.
  • Architects and designers proficient in designing innovative and environmentally sustainable structures.
  • Engineers with expertise in integrating cutting-edge technologies into construction processes.
  • Technicians skilled in operating and maintaining specialized equipment and software.
  • Sustainability experts knowledgeable in green building practices and environmental regulations.
  • IT professionals experienced in managing digital infrastructure and ensuring robust data security measures.
  • Construction workers with extensive experience in prefabrication, modular construction, and adherence to safety protocols.

Resource Histogram:

Resource Number of People
Project Managers 3
Architects 5
Engineers 10
Technicians 8
Sustainability Experts 4
IT Professionals 6
Construction Workers 50
Laborers 30

CONCLUSION

Silicon Valley's development is entering a new phase with the construction plan for the Sustainable Expansion of the Apple Campus area. Through our adoption of cutting-edge technologies, commitment to sustainability, and emphasis on user-centric design, we have raised the bar for both environmental stewardship and building excellence. We are unwavering in our dedication to effectiveness, security, and environmental responsibility as we set out on this adventure. We are ready to build a campus that not only satisfies current demands but also looks ahead to the possibilities and challenges that lie ahead thanks to our combined efforts. Together, we push the envelope in the building industry, promote economic expansion, and build a thriving environment that sparks creativity and innovation.

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Quantitative Methods An Introduction For Business Management

Authors: Paolo Brandimarte

1st Edition

978-1-118-0234, 470496343, 470496347, 978-0470496343

More Books

Students also viewed these General Management questions

Question

3. How much information do we need to collect?

Answered: 1 week ago

Question

2. What types of information are we collecting?

Answered: 1 week ago

Question

5. How quickly can we manage to collect the information?

Answered: 1 week ago