Question
The Bush Oil Company is deciding whether to drill for oil on a tract of land that the company owns. The company estimates that the
The Bush Oil Company is deciding whether to drill for oil on a tract of land that the company owns. The company estimates that the project will cost $6 million today. Bush estimates that once drilled, the oil will generate positive cash flows of $3.9 million a year at the end of each of the next 4 years. Although the company is fairly confident about its cash flow forecast, it recognizes that if it waits 2 years, it will have more information about the local geology as well as the price of oil. Bush estimates that if it waits 2 years, the project will cost $9 million, and cash flows will continue for 4 years after the initial investment is made. Moreover, if it waits 2 years, there is a 85% chance that the cash flows will be $4.2 million a year for 4 years, and there is a 15% chance that the cash flows will be $2.2 million a year for 4 years. Assume that all cash flows are discounted at 10%.
a. If the company chooses to drill today, what is the projects expected net present value?
b. Would it make sense to wait 2 years before deciding whether to drill?
(Yes,No), because the NPV of waiting two years is $_______ and (less,greater) than going ahead and proceeding with the project today.
c. What is the value of the investment timing option?
d. What disadvantages might arise from delaying a project such as this drilling project?
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started