The buyer is not confident on the actual start date of the project, so for this procurement, a target start date and a Fixed Price

The buyer is not confident on the actual start date of the project, so for this procurement, a target start date and a Fixed Price with Economic Price Adjustment contract are used. The buyer and seller agree on 4 quarters per year, and a 3.3% per quarter (Q) of +/- change (delayed + 3.3%/Q, earlier -3.3%/Q). The fixed price for the contract is $1700007.00 CAD, and the target start date is April 18, 2020.

a)What is the quarter(s) change that takes place from the target start date if the actual start date is April 18, 2019? 

b)What is the total contract price with economic price adjustment if the project starts on April 18, 2019 (round answer to a full dollar, no cents)?

Step by Step Solution

3.28 Rating (157 Votes )

There are 3 Steps involved in it

Step: 1

aThe first quarter change would be a 33 increase in price since the project is starting one year lat... blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Corporate Financial Management

Authors: Glen Arnold

5th edition

978-1292178066, 129217806X, 273758837, 978-0273758839

More Books

Students also viewed these Finance questions

Question

Describe the two data analysis options: visual and statistical.

Answered: 1 week ago

Question

=+yni for each i).

Answered: 1 week ago