Question

1 Approved Answer

The buyer is not confident on the actual start date of the project, so for this procurement, a target start date and a Fixed Price

The buyer is not confident on the actual start date of the project, so for this procurement, a target start date and a Fixed Price with Economic Price Adjustment contract is used. The buyer and seller agree on 4 quarters per year, and a 3.3% per quarter (Q) of +/- change (delayed + 3.3%/Q, earlier -3.3%/Q). The fixed price for the contract is $1700007.00 CAD, and the target start date is April 18, 2020.

a)What is the quarter(s) change that takes place from the target start date if the actual start date is April 18, 2019? (Please answer in Box1)

b)What is the total contract price with economic price adjustment if the project starts on April 18, 2019 (round answer to a full dollar, no cents)? (Please answer in Box2)

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access with AI-Powered Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Advanced Financial Accounting

Authors: Thomas H. Beechy

5th Edition

0131236997, 9780131236998

Students also viewed these Finance questions