Question
The calculation of an Economic Order Quantity uses a formula which balances the cost of ordering stock (PER ORDER which may include research, account handling,
The calculation of an Economic Order Quantity uses a formula which balances the cost of ordering stock (PER ORDER which may include research, account handling, supplier meetings and processing time AND if imported, import duties and customs clearance fees etc.) against the UNIT cost of holding inventory (these costs may include warehouse rent, insurance, storage costs etc.). The EOQ is the point where the two costs are equally balanced such that it minimises all costs involved.
- For each of the following independent cases, use the EOQ equation to calculate the economic order quantity:
Case A
Case B
Case C
Annual requirement (in units)
7290
4563
150
Incremental cost per order
$500
$10
$100
Annual carrying cost per unit
$9
$15
$12
Lead time (assume 50 weeks in a year)
4 Weeks
2 Weeks
4 Weeks
Safety stock levels required
400
40
12
EOQ = ( 2*7290*500/9)^0.5= 900 ( for a), 78( for b), 50 ( for c)
- Calculate the Reorder point for all three case with safety stock
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started