Question
The California Department of Transportation (Caltrans) is looking to replace an aging highway overpass. The work requires closing two lanes of the highway, which causes
The California Department of Transportation (Caltrans) is looking to replace an aging highway overpass. The work requires closing two lanes of the highway, which causes traffic delays, and hence on-time completion of the project is critical. If the contractor who is awarded the project works diligently, the project is completed on time with probability 0.9. However, the contractor can slack off to save $10M in overtime costs, in which case the project is completed on time with probability 0.1.
Caltrans offers a contract that consists of a base payment and a bonus for on-time completion. Assume that the base payment is large enough so that the contractor would sign the contract given any of the bonuses listed below.
Of the bonuses listed below, which is the smallestthat still motivates the risk-neutral contractor to work diligently?
a)$9M
b) $7M
c)$5M
d) $11M
e) $13M
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started