The Carry - on Luggage Company must set up an assembly line for a wheeled carry - on bag. Forecasts show that 4 4 units

The Carry-on Luggage Company must set up an assembly line for a wheeled carry-on bag. Forecasts show that 44
units per hour should be produced. The tasks required, task times, and precedence relationships are as follows:
Click here for the Excel Data File
a. What is the takt time?
b. What is the theoretical number of workstations?
c. Assign the tasks to the workstations to balance the line using the longest operating time rule.
d. What is the efficiency of the balanced line?
image text in transcribed

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Beetons Book Of Household Management

Authors: Arlene Morriso

1st Edition

1721995153, 978-1721995158

More Books

Students also viewed these General Management questions

Question

a score of 70 or higher on the test?

Answered: 1 week ago