The cash flows and Net salvage value of Project B is given the following table: Year Cash flows Salvage Value 0 -5,800 5,800 1 2,100
The cash flows and Net salvage value of Project B is given the following table: Year Cash flows Salvage Value 0 -5,800 5,800 1 2,100 2,200 2 1,400 1,600 3 1,600 1,200 4 1,800 600 Given the cost of capital is 9%, Calculate the NPV for its Economic Life and determine what are its economic life and physical life of Project B?