Question
1 Approved Answer
The chart below shows the network diagram for a project. The duration in weeks for each activity is shown beneath the activity letter. For instance,
The chart below shows the network diagram for a project. The duration in weeks for each activity is shown beneath the activity letter. For instance, the duration for activity A is one week.