The Chief Operations Officer ( COO ) of a firm that moves earth in preparation for the construction in Abbotsford has identified the activities and
The Chief Operations Officer COO of a firm that moves earth in preparation for the construction in Abbotsford has identified the activities and their durations for each stage of an operation to prepare a difficult stretch of motorway see Table below The COO needs to know how long the project will take and which are the critical activities.
a Identify the three goals of a project and describe how the project manager achieves them.
b Draw the network diagram for the motorway project.
c Calculate the latest and earliest event times for the project activities.
d Show the critical path of the project and indicate the total days to complete the project.
e Develop the Gantt Chart for the project.
Table
Activity Duration Preceding Activities
A
B
C
D B
E B
F B
G AD
H AD
I F
J F
K CJ
L HEI,K
M CJ
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started