The city of Charleston, SC is opening a new performing arts center. You have been given the following tasks which must be accomplished to complete

The city of Charleston, SC is opening a new performing arts center. You have been given the following tasks which must be accomplished to complete the project.

Activity | Duration (in weeks) | Immediate Predecessor

A | 8 | -

B | 2 | A

C | 3 | A

D | 6 | B

E | 4 | B, C

F | 7 | C

G | 10 | D, E, F

Draw an Activity-on-Node Network to represent this project. Find the critical path. Please help me complete forward and backward pass to derive the earliest start (ES), earliest finish (EF), latest start (LS), latest finish (LF) and slack times for all of the activities. Once you have calculated the slack times for all activities, sum the slack times over all activities and enter that total number as your final answer.

Enter your answer as an integer. E.g. if Slack_A = 0, Slack_B = 0, Slack_C=20, Slack_D=7, Slack_E=0, Slack_F=6, and Slack_G =4 enter 0 0 20 7 0 6 4 = 37

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Essentials Of Enterprise Risk Management

Authors: Rick Nason, Leslie Fleming

1st Edition

1947098365, 978-1947098367

More Books

Students also viewed these General Management questions

Question

7 How can a culture encourage ethical (or unethical) behaviour?

Answered: 1 week ago