The company received a $5,000,000 contract to construct a high-rise building at an estimated cost of $4,200,000. The contract starts in March 2020, and ends

The company received a $5,000,000 contract to construct a high-rise building at an estimated cost of $4,200,000. The contract starts in March 2020, and ends in December 2022. The Company recognizes its revenue using the Percentage of Completion Method.

2020 2021 2022
Cost to Date 1.000.000 2.100.000 4.200.000
Estimate cost to complete 3.000.000 2.100.000 -
Progress Billing during the year 1.000.000 2.800.000 1.200.000
Cash Collected during the year 800.000 2.000.000 2.200.000

Required:

1. Calculate the percentage of completion and gross profit for the year 2020-2022!

2. Make journals to record transactions related to the contract!

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Modern Advanced Accounting In Canada

Authors: Hilton Murray, Herauf Darrell

7th Edition

1259066487, 978-1259066481

More Books

Students also viewed these Accounting questions

Question

Write down the Limitation of Beer - Lamberts law?

Answered: 1 week ago

Question

Discuss the Hawthorne experiments in detail

Answered: 1 week ago

Question

Explain the characteristics of a good system of control

Answered: 1 week ago

Question

State the importance of control

Answered: 1 week ago

Question

Whats My Comfort with Change?

Answered: 1 week ago