Question
The company 'Rise 42' is concern with the quality and accuracy of estimation so project managers are currently reviewing the different methods the company uses
The company 'Rise 42' is concern with the quality and accuracy of estimation so project managers are currently reviewing the different methods the company uses for estimating schedule, cost and resource. In most of 'Rise 42's' estimation of project activities there is significant uncertainty associated with estimating time or cost. At a recent Senior Management Team (SMT) meeting, the new VP for Marketing and Communications stated that "....time is everything: our survival depends on getting the products to our customers first...... time and accuracy are not the issue".
The VP for Marketing and Communications also suggested that "Top-down" estimating method must be used for all projects given the high uncertainty in estimating schedule, cost resources and other activities. He highlighted other conditions for preferring certain estimation methods including the following:
- Strategic decision making
- Importance of Cost and Time
- Small internal projects
- The customer wants details
- Unstable scope
A. Do you agree with the VP for Marketing and Communications comments that "Top-down" estimating method must be used for all projects - why or why not?
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started