The Consolidated Bank of Ghana (CBG) is planning to install a new computerized accounts system. Bank management has determined the activities required to complete the

  1. The Consolidated Bank of Ghana (CBG) is planning to install a new computerized accounts system. Bank management has determined the activities required to complete the project, the precedence relationships of the activities, and activity time estimates as followS

Time

Estimates

(weeks)

Activity

Description

Predecessor

a

m

b

A

Position Recruiting

-

5

8

17

B

System Development

-

3

12

15

C

System Training

A

4

7

10

D

Equipment training

A

5

8

23

E

Manual System Test

B, C

1

1

1

F

Preliminary System Changeover

B, C

1

4

13

G

Computer-Personnel Interface

D, E

3

6

9

H

Equipment Modification

D, E

1

2.5

7

I

Equipment testing

H

1

1

1

J

System Debugging and Installation

F, G

2

2

2

K

Equipment Changeover

G, I

5

8

11

Question 2(c). When will the computerized accounting system be ready for use?

  1. Management of CBG is not happy with the completion time in Question 2(c) and wants the project completed earlier than that. You are given the following additional activity information

Activity

Crash Time (weeks)

Activity Cost (GH)

Normal

Crash

A

7

4,800

6,300

B

9

9,100

15,500

C

5

3,000

4,000

D

8

3,600

5,000

E

1

0

0

F

3

1,500

2,000

G

5

1,800

2,000

H

3

0

0

I

1

0

0

J

2

0

0

K

6

5,000

7,000

i. Prepare a table of Allowable Crash Time and Crash Cost per Week for each activity. (5 marks)

Management of CBG can offer a maximum of GH800 per week to enable the project manager reduce the project completion time:

ii. prepare a table for the crashing procedure. (5.5 marks)

iii. when will the project now be completed? (0.5 mark)

iv. what is the total extra cost to management of CBG? (1 mark)

v. If management of CBG wishes the computerized accounting system to be ready at week 30, what will be the total extra cost to CBG? (2 marks

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Financial Accounting A Business Perspective

Authors: Roger H. Hermanson, James Don Edwards

7th Edition

0072289988, 978-0072289985

More Books

Students also viewed these Accounting questions