Question

1 Approved Answer

the construction activity for the year-end 31 December 2020, are as follows: project contract price costs incurred to 31/12/2020 estimated costs to complete billing to

the construction activity for the year-end 31 December 2020, are as follows:

project contract price costs incurred to 31/12/2020 estimated costs to complete billing to 31/12/2020 cash collections to 31/12/2020
AB $2,000,000 $600,000 $1,400,000 $450,000 $410,000

Required:

1) Prepare a schedule by project, showing clearly the amount of gross profit (loss) of the project before deducting selling, general, and administrative expenses for the year ended 31 December 2020 using the percentage-of-completion method. (based on estimated costs.)

2)Based on the schedule, show the amount of gross profit ( or loss) before selling, general, and administrative expenses for the year ended 31 December 2020, which would be reported if the following method are used:

(I) the cost-recovery method.

(II) The percentage-of-completion method ( based on estimated costs)

3) Prepare all the necessary general journal entries for the project AB for the financial year 2020, using the percentage-of-completion method.

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Wiley Federal Government Auditing Laws Regulations Standards And Practices

Authors: Edward F. Kearney, Roldan Fernandez, Jeffrey W. Green, David M. Zavada

2nd Edition

1118555856, 978-1118555859

More Books

Students also viewed these Accounting questions