The construction project consists of 3 activities with the following durations: 1. Design, with a duration normally distributed with a mean of 90 days and

The construction project consists of 3 activities with the following durations:

1. Design, with a duration normally distributed with a mean of 90 days and a standard deviation of 15 days

2. Procurement, with a duration of 100 days, and a standard deviation of 30 days

3. Construction: with a duration of 120 days and a standard deviation of 10 days Activity 1 and 2 are performed in parallel (i.e. simultaneously).

The activity 3 cannot be started until activity 1 and 2 are finished. After running a simulation with at least 1,000 replications, what is the expected total duration of the project and the probability of this duration being less than 200 days?

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

More Books

Students also viewed these Accounting questions