The controller for Wolfe Machining has established the following overhead cost pools and cost drivers:
Overhead cost Pool | Budgeted overhead cost | cost driver |
Machine setups | $240,000 | number of setups |
Material Handling | 90,000 | Units of raw material |
Quality control inspection | 48,000 | Number of inspection |
Other overhead costs | 160,000 | machine hours |
total | $538,000 |
Over Head cost pool | Budgeted Level for Cost driver | Pool Rate |
Machine setups | 200 setups | $1,200 per setup |
Material Handling | 60,000 units | $1.50 per unit |
Quality Control | 1,200 inspections | $40 per inspection |
Other overhead | 20,000 machine hours | $ 8 per machine hour |
Order no. 715 has the following production requirements: Machine setups: 5 Raw material: 10,700 units Inspections: 19 Machine hours: 790 a.[10 points] Compute the total overhead that should be assigned to order no. 715 by using activity-based costing.
b. [10 points] Suppose that Wolfe were to use a single, predetermined overhead rate based on machine hours. Compute the rate per hour and the total overhead assigned to order no. 715. .
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started